Resolving agency issues in client-contractor relationships
DECISION SCIENCES INSTITUTE
Resolving agency issues in client-contractor relationships: The Merck Innovation Center
(Instructional Case)
ABSTRACT
The management of relationships has been acknowledged as a crucial element of project
success. However, agency related issues such as goal conflict, information asymmetry or
opportunistic behavior can make this a real challenge. Steven and Mark – program
managers for One Global Headquarters at Merck – developed their own way on how to deal
with this challenge in a complex and uncertain environment. This case study will provide
unique insights into their approach and motivation.
KEYWORDS: project management, agency theory, project success, principal agent
relationship
Fig.1 Merck Innovation Center and Emmanuel-Merck-Platz in Darmstadt, Germany (reproduced with
permission from Esch (2018))
1
Resolving agency issues in client-contractor relationships
A FACELIFT FOR A 350-YEAR-OLD COMPANY
In 2015, after several large acquisitions transformed its businesses, Merck KGaA1 underwent
a re-branding into the single brand Merck. Merck is a diversified pharmaceutical, life sciences
and chemicals group founded in 1668 and ever since headquartered in Darmstadt, Germany.
The company employs approximately 52,000 people around the world, with 11,000 in North
America and about the same number in Germany (Merck, 2019). The company invested
US$ 565m in Capex world-wide in 2015, including a large number of construction projects
(Merck, 2016).
The new brand was designed to position the organization as an innovative science and
technology company as prior analysis suggested that its culture had to undergo a
transformative change. It was also recognized that architecture, in particular at the
headquarters, conveys a strong message to customers, partners, the community, and
employees and that the architecture needs to represent the transformative change as well.
On this basis, the program One Global Headquarters (OGHQ) was initiated in 2014 with the
aim of completion by 2018, when the company celebrated its 350-year anniversary. The
program consisted of about 90 interdependent construction projects of various sizes, shapes
and forms at the headquarters in Darmstadt with a total investment of more than US$ 200m.
The program was led by two internal managers – Steven and Mark – who mainly focused on
strategy and governance issues and were supported by a program management team of
internal and external experts to oversee the high number of projects. External experts were
hired in all cases, in which internal resources were considered inadequate or insufficient to
stay in control of architectural quality, schedule and budget, all of which were non-negotiable.
At the heart of the program was the development of the Innovation Center and the adjacent
Employee Restaurant (Figure 1 and 2), which was described by its architects Henn as
follows (Henn, 2019):
“The Innovation Center will be used to cooperate temporarily in interdisciplinary
teams and to communicate both internally and externally. While the newly developed
public square (…) orientates the company towards the city, the Innovation Center
opens it to the interior. There are three levels which are set back from one another so
that they are to a large extent visually linked. Levels can be changed using arched
ramps. These connections, like the bridges joining the segments at individual levels,
are highly frequented meeting places where the direct exchange of information
among knowledge holders is encouraged. In passing, building users can be inspired
by the work of their colleagues and prompted to engage in discussions. Different
demands on the workplaces – concentration, communication, cooperation – find
spatial expression in a flowing transition. Team communication takes place in the
spacious internal area on each floor. Single-person office cells along the façade
provide space for activities requiring concentration and intensive thought. The
company restaurant is connected to the Innovation Center on several levels. It will
assume essential functions on the currently decentralized staff canteens, some of
1
Founded in 1668 in Darmstadt, Germany, Merck is the world’s oldest pharmaceutical and chemical company. In the 19th
century, the success of its export business to the United States led to the establishment of an office in New York in 1887, which
gave rise to the establishment of a separate entity four years later. In 1917, during World War I it was expropriated. Ever since,
there are two different, unaffiliated companies that use the name MERCK. Globally, except in the United States and Canada,
Merck KGaA, and its affiliates are named simply “Merck”. In the United States and Canada, Merck KGaA uses its firm name
“Merck KGaA, Darmstadt, Germany,” and its businesses operate under “EMD Serono” in biopharma, “MilliporeSigma” in life
science and “EMD Performance Materials” in the materials business. The other company, Merck & Co., Inc., Kenilworth, NJ, US
holds the rights in the trademark MERCK in the United States and Canada. All references to the name Merck in this case study
refer exclusively to the former.
2
Resolving agency issues in client-contractor relationships
which are to be decommissioned. The restaurant will become a meeting place for
numerous employees from the various parts of the site.”
Fig. 2 Typical floor space in the Merck Innovation Center (reproduced with permission from Esch
(2018))
EUROPE’S LEADING CONSTRUCTION MARKET
The context for this case study is Europe’s leading construction market with the continent’s
largest building stock: Germany. The construction sector in general is one of the largest
contributors to the world economy and a key industry in most countries. A recent global
survey found that the productivity of the sector has by far trailed that of almost all other
industrial sectors over the past decades, thus offering huge opportunities for improvement
(Barbosa et al, 2017). While it was found that low productivity performance in construction is
not uniformly distributed, with big variations between countries and subsectors, there are still
common reasons for it. Among those reasons stands the observation, that
“Construction is highly fragmented. Contracts have mismatches in risk allocation and
rewards, and often inexperienced owners and buyers find it hard to navigate in an
opaque marketplace. The result is poor project management and execution,
insufficient skills, inadequate design processes, and underinvestment in skills
development, R&D, and innovation.” (Barbosa et al, 2017, p. 8)
The study concludes that market failures and external factors compromise how the industry
functions and result in low productivity of firms of all sizes. Overall, low labor productivity, as
3
Resolving agency issues in client-contractor relationships
well as poor project management can be directly linked to project failures in terms of cost
overruns and delays that are often observed in construction projects.
The German construction sector is a good representation of this situation. The abovementioned study finds it to be almost average-ranking in terms of both construction labor
productivity and its growth. In 2018 the industry’s added value contributed US$ 178bn or
5.3% to the German economy (Statistisches Bundesamt, 2019). During the past decade,
after a cyclical downturn of the industry, many large national construction firms, whose core
competence was the efficient execution of large turn-key construction projects, left the
market and their place was taken by medium-sized, often family owned, companies
specializing in particular trades such as concrete works, façade-works or interior fit out.
Architects typically work in small- to medium-sized specialized practices and subcontract
engineering design work to specialized engineering firms. Deliverables, their quality and, to
some extent, the fees of architects and engineers are regulated by national legislation.
It has been widely argued that contractors, like all other partners in a project, should become
fully involved as early as possible in order to participate in the evolution of the final design by
contributing their knowledge and expertise and become an integrated network partner.
However, many public and private clients defer the final investment decision by means of
their corporate governance until basic design is completed and cost estimates by the
consultants become firmer. Hence, only after the final investment decision is made by the
client, the architect and engineers start to prepare the tendering documents for all trades and
procurement packages in order to avoid sunk costs in case the final investment decision is
negative. Various different procurement models are available, whereas the traditional
competitive tendering is still prevalent. More innovative methods like open book contracts are
in its infancy in Germany and many clients and contractors do not know how to
accommodate them in their corporate governance and are not familiar with the required
changes in behavior and attitude.
Many spectacular project failures both in the public as well as in the private sector have been
credited to an adversarial and fragmented project environment based on suboptimal
contractual arrangements that often resulted in claims and litigation. Major customers and
powerful players of the German construction industry have recognized the necessity of better
collaboration and better contracts with their initiative TeamBuilding under the slogan “For a
Better Collaboration in the Construction Industry”, which was started in 2017 (Initiative
Teambuilding, 2019).
ONE GLOBAL HEADQUARTERS – THE MAIN ACTORS
As previously mentioned, the OGHQ program was led by Steven and Mark. Steven is a
program and project manager with more than 30 years’ experience. He is a chemical
engineer with a PhD by training, however moved into the management of major projects
within Merck several times during the past 20 years. Since then he has been responsible for
R&D, construction and organizational projects ranging from tens to several hundred million
US$ with the OGHQ program being the largest and most important so far. His background
gives him a very good understanding of the client’s organization as well as project
governance. Mark is a qualified architect and joined Merck only shortly before the program
by direct initiative of Merck’s CEO. He has a long career in the construction industry with vast
experience as architectural lead for a major contractor in Germany. This gives him specific
expertise in architecture as well as in the nuances of the German construction market. He
likes to stress the need for a good start in any project and compares it to a 100m sprint that
4
Resolving agency issues in client-contractor relationships
is always lost, if the runner doesn´t get a good start. This theme became a proverb in the
program.
Steven and Mark are supported by a team of internal and external experts. Within the
program, Claire is the project manager for the Innovation Center and Employee Restaurant.
Claire is a qualified architect, who worked as an independent architect before joining Merck
20 years ago. She has been trusted with major and important construction projects since.
Based upon her track record, Steven had lobbied hard to have her assigned to the program.
Other key players were Peter, the architect’s project leader who had the overall responsibility
for the design of the buildings as well as the construction management, and John, the
structural engineer, who had to find ways to make Peter’s ambitious design feasible and
affordable while also complying with building regulations. John heads the Berlin office of his
structural engineering company, which is one of the best in the country with a vast
experience in challenging designs. Peter led many ambitious construction projects for large
corporate clients in Germany and China and is supported by Paul, a civil engineer by
training, who successfully acted as a construction manager for various projects.
Worth mentioning here are also Frank, who is Merck´s procurement manager for the
program with an engineering background, and Lilian, a civil engineer and quantity surveyor,
who is part of a team of external specialists from the project management consultancy Drees
& Sommer. She and her team were specifically hired for the program to complement all
required competences of the program management team.
CONCRETE AND STEEL WORKS – BACKGROUND
Considering the general environment outlined earlier, Steven and Mark were faced with a
dilemma: they either follow the traditional way of procurement through competitive tendering,
which is likely to create the basis for an adversarial environment with all its negative
consequences, or they use more innovative forms like open book contracts, which are
difficult to accommodate within Merck’s corporate governance and the industry isn’t very
familiar with them either. However, they did not want to adopt an only partially suitable
solution and decided to explore new collaborative ways of selecting contractors. They were
conscious of some of the issues often present in client-contractor relationships like goal
conflict, information asymmetry, trust or opportunistic behavior and tried to identify ways to
overcome these. They assumed that these issues contribute to the adversarial environment
and hence, are inhibitors of project success. As the OGHQ program had very high strategic
importance within Merck, Steven and Mark did not want to risk the project being late, over
budget or of mediocre quality. Based on the procurement of concrete and steel works for the
Innovation Center and Employee Restaurant their approach to collaborative procurement is
explained in the following.
The tendering package for concrete and steel works was chosen for two reasons: Firstly, the
intricate architectural design was highly challenging as it required complicated and fair-faced
concrete surfaces, wide ceiling spreads, and floors resting on very few supporting pillars (see
Figure 3a to d). To build such a complex concrete-cum-steel structure without flaws requires
a tremendously high quality of craftmanship in formwork, ironworks and concrete works,
which only few contractors are able to deliver. In such a case it is paramount for the project’s
eventual success, that the bidding contractors do not under-estimate the complexity and
difficulties of the required work and erroneously bid too low or beyond their capabilities.
Hence, Steven and Mark concluded that in such a case tendering cannot be conducted
based on price only, but that a collaboration based on trust needs to be developed with the
contractor to manage the complexity of the project. Secondly, requirements the structural
5
Resolving agency issues in client-contractor relationships
design for the tendering documents was based upon, were exacerbated at a late stage
during the procurement phase, rendering several requirements and material take-offs2
obsolete in some parts. As the timely laying of foundations was imminent, certain structural
design questions relevant to pricing had to be put to rest during the procurement process
under the mutual understanding that they were to be sorted out fairly later on. Steve and
Mark were confident that their collaborative approach would be able to accommodate this
difficult situation. Otherwise an incomplete design basis would result in extensive claims or
overpricing due to incalculable risks, which they obviously wanted to avoid.
Fig. 3 a and b: Concrete ramps in the MIC during construction and upon completion (reproduced with
permission from Esch (2018))
Fig. 3 c and d: View into a stair well during construction and upon completion (reproduced with
permission from Esch (2018))
2
Material take-offs are used in engineering and construction, and the term refers to a list of materials with quantities and types
(such as specific grades of steel) that are required to build a designed structure or item. This list is generated by analysis of a
blueprint or other design document.
6
Resolving agency issues in client-contractor relationships
CONCRETE AND STEEL WORKS – PROCUREMENT PROCESS
During the pre-contract phase Steven, Mark and Claire put a high emphasis on the quick
build-up of project knowledge with the potential contractors who were about to join the
bidding process. Naturally, there is a big information asymmetry about the project and the
nature of the task between the principal partners, i.e. client, architect, engineers – who have
worked on the project for months or even years – and the incoming bidders – who are just
familiarizing themselves with the material provided – which puts the latter at a disadvantage.
Steven, Mark and Claire had planned to overcome this information asymmetry through a
dedicated information exchange including discussions with all bidders on an individual basis
throughout the procurement process, which is summarized in Table 1. This also allowed
them early on to build a collaborative relationship based on trust with the bidders which they
hoped would be carried through to the post-contract award phase of the project.
Stage
t
1
2
3
4
5
6
7
(1)
(2)
8
9
(3)
10
11
12
(4)
Tendering activity
Bidders
Request for interest in bidding
Distribution of original tender
documents
Individual workshops – workshop 1
Submission of quotes
Individual workshops – workshop 2
Revision of quotes #1
Amendment of tender documents
based on new regulatory
requirements and
Submission of indicative quote
Individual risk mitigation workshops
– workshop 3
Revision of quotes #2
Contract negotiations
Contract signed
Table 1. Procurement process; disturbance symbol (
23
14
Calendar week
2015
4 – 12
13
8
5
5
5
2
16 – 17
22
23
25
27 – 29
2
2
30
30
2
1
1
33
36
38
) represents changed requirements.
Steven, Mark and their team intended to achieve the following objectives with this approach:
x
x
x
x
x
Build a mutual understanding of technical and qualitative building requirements.
Familiarize bidders with the planning content of the previous design work as well
as its limits and challenges.
Clarification of technical issues and time schedules for both sides.
Preparation of a common basis for realistic and comparable pricing.
To become mutually acquainted with the acting persons and creation of a mutual
base of understanding and trust.
Claire and Frank identified 23 pre-qualified contractors who they provided with a brief
introduction to the project and asked for an expression of interest for inclusion in the bidding
process (stage 1). They received 14 positive responses and sent the full tendering package
to these contractors (stage 2). Upon closer inspection of the information provided, six
contractors decided not to engage in the bidding process any further and the remaining eight
were invited to individual day-long workshops (stage 3). During the workshops (workshop 1),
7
Resolving agency issues in client-contractor relationships
Claire explained rationale and situation of the project, in particular the challenging time-line
that was given the highest priority by Merck, as well as the organization of the construction
site; Peter explained building concept and design and presented examples and challenges in
making the fair-faced concrete surfaces; John explained the structural design concept and
Paul and Lilian captured feedback on a previously drafted schedule considering site logistics
and interdependencies with other contractors. After this introduction, technical questions by
the bidders were addressed and discussed extensively.
This workshop was specifically designed to establish a good working relationship and
demonstrate the collaborative approach chosen for this project. However, discussions on
pricing were completely excluded at this point and the bidders were asked to prepare their
quotes under due consideration of the workshop results.
Three bidders refrained from submitting a quote after the workshops, whereas the remaining
five submitted their quotes on time (stage 4). As shown in Figure 4, quoted prices were
spread out significantly at this point (t=1) with a variance of more than 50%. After evaluation
of the quotes the bidders were invited to another set of individual workshops (workshop 2),
which were centered around the results of the Lilian’s and Peter’s check and individual items
of the quotes, where pricing appeared to be off or inconsistent (stage 5). As a result, the two
lowest priced bidders raised their price, whilst the most expensive one lowered his, and the
spread in pricing of the now technically comparable quotes had fallen by half (t=2; stage 6).
All these intensive discussions also provided interesting insights for Steven, Mark and their
team into competence and general attitude of the bidder and their representatives, who were
about to become future partners in the project. This allowed them to draw conclusions on the
contractors’ collaborative approach and how it developed over time, i.e. they could see if
collaboration is really engrained in the contractors’ thinking and doing or if it is just a
marketing approach.
relative quoted price
160%
140%
Bidder A
Bidder B
120%
Bidder C
Bidder D
100%
Bidder E
80%
20
t=1
25
t=2
30
t=3
t=4
User generated content is uploaded by users for the purposes of learning and should be used following Studypool’s honor code & terms of service.
Try it now!
Get 20% Discount on This Paper
How it works?
Follow these simple steps to get your paper done
Place your order
Fill in the order form and provide all details of your assignment.
Proceed with the payment
Choose the payment system that suits you most.
Receive the final file
Once your paper is ready, we will email it to you.
Our Services
Ace Writing Center has stood as the world’s leading custom essay writing services providers. Once you enter all the details in the order form under the place order button, the rest is up to us.
Essays
Essay Writing Services
At Ace Writing Center, Nowadays, students normally have extremely busy schedules. You will note that some of them have to take on some evening or weekend jobs in order to get some income that can help them to sustain in college or in the university. This can deny them a chance to write all the essays given. Others usually get bombarded with a lot of work by their lecturers. This can still delay such students from working on all their essays. However, some of them usually try to work on all these essays but end up delivering their work late. This can prevent them from graduating since most lecturers are strict on deadlines. If you want to write a business essay, the wise way is to hire an outstanding essay writing service like us, so that you can get the best results.
If you are keen, you will note that many companies usually overcharge their customers. Some of them are there only to make money. And in reality, they really don’t care to build a long term commitment with students. You should not choose such companies. You should take your time and choose a reliable company to work with. Ace Writing Center is the ultimate solution for you. We have been offering our writing service for more than 7 years. This is a clear indication that you will get quality essay writing service. We have a wide range of writers who can work on any business essay that you might have. We believe in doing extensive research so that we can provide quality work to all our clients.
.
Admissions
Admission and Business Papers
Have you ever had to write an admission essay for college? The majority of students face the same issues when applying to a university or college and many in such situations decide they need professional help to cope with this matter. They get in a situation when the deadline keeps coming closer but lack motivation to start because they are just not sure if their writing skills are strong enough. We have a solution for you! Ace Writing Center is the best admission essay writing service with a large professional team and years of experience in providing high-quality papers to students of all levels and faculties. The mission of our team is to help students make their dreams of entering a good college come true and that’s what we offer!.
Editing
Editing and Proofreading
Sometimes all the words for your paper just flow out of your mind and into your fingers. You type quickly at your keyboard and there they are, your beautiful words right there on the screen. But you have no idea how to polish it up. You may be wishing there was a paper writing service that offered this type of writing service. Look no more! Here at Ace Writing Center, we offer you an editing and proofreading option that you can't find anywhere else..
Coursework
College Essay Writing
In case you are familiar Ace Writing Center, you know the way to distinguish a better company from a cheap one exactly. First of all, poor service website does not have a sufficient support. We think support team is an essential part of success; it has to answer all clients’ questions and be a connecting link between clients and their writers. On our web-service you will get answers about anything you need and your writer will receive all your instructions, assignments and requirements exactly and swiftly. A writing service that we run has got a flexible pricing system that will save you from senseless wastes and many bonus systems that let you sparing money for something important for you.